Liberty Ostrava restarts Blast Furnace no. 2 following maintenance upgrades

2020-08-25

Aug. 25, 2020 - After almost a four-month shutdown, LIBERTY Ostrava has restarted Blast Furnace No. 2 following essential repairs worth more than CZK 44 million to upgrade and modernise the furnace, which started its first campain almost 70 years ago. The restart highlights the ability of the LIBERTY Ostrava business to flex its operations in line with market demand.


Pascal Genest, CEO of LIBERTY Ostrava, said: “The temporary shutdown of the furnace allowed us to respond flexibly to the slump in steel demand due to the coronavirus pandemic and to reduce the metal inventory built for the start of the construction season. We are very pleased that the repairs have been carried out successfully and that we have been able to deliver on our commitment to restart the furnace by the end of August. The ability to manage the Blast Furnace in this way highlights the plant’s flexibility, which will help the business as it looks to improve its long term economic and environmental sustainability.”


After the furnace had cooled down for 40 days, from its normal 2,300 °C operating temperature, an extensive repair programme started. This programme included the replacement of the cooling piping, the modernization of the furnace cooling system as well as minor repairs to the hot-blast stoves, charging machines, skip tracks and the dust collector. A number of companies from the across the region, such as KADAMO, Stavby OMO, Hutní montáže Slovakia, and Speciální výškové práce – Roland Babka, supported the LIBERTY Ostrava team in effecting the repairs.


In line with an old steelmakers´ tradition, the Chief Smelter ignited the burners of the Blast Furnace with a torch lit by the fire from the other Blast Furnace. Václav Habura, Chief Operation Officer at LIBERTY Ostrava, explained: “The first tapping of hot metal will follow after about 20 hours of the restart, and it will take a few days for the furnace to produce hot metal which can be used for steelmaking.”


Blast Furnace no. 2, which is 35 meters high and whose structure measures 70 meters, was first lit on October 1, 1952. It can produce up to 3,200 tonnes of hot metal per day.

About Us Site Map Service Our Partners Links Inquiry Contact FAQ Privacy Statement Technical Support

Sponsored by: ACRI (The Association of China Refractories Industry), Tangshan YinNaiLian E-Business Co., Ltd.

Copyright © 2005-2020 Refractories Window All Rights Reserved

Tel: +86-315-5918500 Fax: +86-315-5918828 Email: info@refwin.com

ICP经营许可证编号: 冀B2-20060049 ICP备案号: 冀ICP备17015545号

冀公网安备 13024002000198号 营业执照